type, title, description, jurisdiction, legislature, session, identifier, citation, classification, subjects, status, primary_sponsors, version_count, action_count, vote_count, first_action, last_action, source, source_identifier, source_url, source_hash, vintage, source_snapshot, retrieved_at, confidence, tags
| type | title | description | jurisdiction | legislature | session | identifier | citation | classification | subjects | status | primary_sponsors | version_count | action_count | vote_count | first_action | last_action | source | source_identifier | source_url | source_hash | vintage | source_snapshot | retrieved_at | confidence | tags | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Bill | UTILITY-HIGH-VOLTAGE ELEC LINE | Amends the Public Utilities Act. Provides that a public utility seeking to construct a high-voltage electric service line and related facilities (Project) must show that the utility has held a minimum of 2 pre-filing public meetings to receive public comment concerning the Project in each county where the Project is to be located, no earlier than 6 months prior to filing an application for a certificate of public convenience and necessity from the Illinois Commerce Commission. Provides that a public utility seeking to construct a Project shall include with the application for a certificate of public convenience and necessity to the Commission a list containing the name and address of each owner of record of the land included in the primary or alternate rights-of way for the Project as disclosed by the records of the tax collector of the county in which the land is located, as of not more than 30 days prior to the filing of the application. Provides that a public utility seeking to construct a Project may not ask for an easement for more ground than what it has filed with the Commission. Provides that a public utility that has been granted a certificate of public convenience and necessity for the purpose of making land surveys and land use studies shall provide a second notice to the owner of the property, identifying the date and time when land surveys and land use studies will begin on the property and informing the landowner of his or her right to be present when the land surveys or land use studies occur. Provides that the second notice shall also indicate whether the certificate of public convenience and necessity has been granted, whether it has been stayed by a court at the time of surveying, and indicate that, should the certificate of public convenience and necessity not be granted or is stayed by a court, the public utility has no right to enter the property. Provides that the notice shall also clearly indicate the property the public utility wishes to survey, and where the landowner can call to deny permission if the certificate of public convenience and necessity has not been granted or has been stayed by a court. Effective immediately. | us/states/il | Illinois General Assembly | 99th | SB 1726 | Illinois SB 1726 (99th) |
|
enacted | 3 | 60 | 2 | 2015-02-20 | 2015-08-18 | openstates | ocd-bill/883a6030-cef6-49d8-8a50-61c753876e6e | http://ilga.gov/legislation/BillStatus.asp?DocNum=1726&GAID=13&DocTypeID=SB&LegId=88474&SessionID=88&GA=99 | 1b006d21dbbc415d50fbb1e057c2d45db7fd9a8c1ab313314abe0f3df3674b87 | 2026-07-01 | https://data.openstates.org/daily/2026-07-01/public.pgdump | 2026-07-06 | reported |
|
Illinois SB 1726 (99th) — UTILITY-HIGH-VOLTAGE ELEC LINE
Amends the Public Utilities Act. Provides that a public utility seeking to construct a high-voltage electric service line and related facilities (Project) must show that the utility has held a minimum of 2 pre-filing public meetings to receive public comment concerning the Project in each county where the Project is to be located, no earlier than 6 months prior to filing an application for a certificate of public convenience and necessity from the Illinois Commerce Commission. Provides that a public utility seeking to construct a Project shall include with the application for a certificate of public convenience and necessity to the Commission a list containing the name and address of each owner of record of the land included in the primary or alternate rights-of way for the Project as disclosed by the records of the tax collector of the county in which the land is located, as of not more than 30 days prior to the filing of the application. Provides that a public utility seeking to construct a Project may not ask for an easement for more ground than what it has filed with the Commission. Provides that a public utility that has been granted a certificate of public convenience and necessity for the purpose of making land surveys and land use studies shall provide a second notice to the owner of the property, identifying the date and time when land surveys and land use studies will begin on the property and informing the landowner of his or her right to be present when the land surveys or land use studies occur. Provides that the second notice shall also indicate whether the certificate of public convenience and necessity has been granted, whether it has been stayed by a court at the time of surveying, and indicate that, should the certificate of public convenience and necessity not be granted or is stayed by a court, the public utility has no right to enter the property. Provides that the notice shall also clearly indicate the property the public utility wishes to survey, and where the landowner can call to deny permission if the certificate of public convenience and necessity has not been granted or has been stayed by a court. Effective immediately.
Version chain
The bill's text revisions, in order — the diff chain from filing to enrollment.
Votes
- Third Reading — 116–0 (pass) · lower
- Third Reading — 55–0 (pass) · upper
Sponsors
- Chapin Rose — primary (person)
- Linda Chapa LaVia — cosponsor (person)
- Patrick J. Verschoore — cosponsor (person)
Timeline
The legislative action history — every referral, reading, and vote.
- 2015-02-20 Filed with Secretary by Sen. Chapin Rose
filing - 2015-02-20 First Reading
reading-1 - 2015-02-20 Referred to Assignments
referral-committee - 2015-03-11 Assigned to Energy and Public Utilities
referral-committee - 2015-03-20 Senate Committee Amendment No. 1 Filed with Secretary by Sen. Chapin Rose
amendment-introduction - 2015-03-20 Senate Committee Amendment No. 1 Referred to Assignments
referral-committee - 2015-03-24 Senate Committee Amendment No. 1 Assignments Refers to Energy and Public Utilities
- 2015-03-26 Senate Committee Amendment No. 1 Adopted
amendment-passage - 2015-03-26 Do Pass as Amended Energy and Public Utilities; 017-000-000
committee-passage - 2015-03-26 Placed on Calendar Order of 2nd Reading April 14, 2015
- 2015-04-17 Senate Floor Amendment No. 2 Filed with Secretary by Sen. Chapin Rose
amendment-introduction - 2015-04-17 Senate Floor Amendment No. 2 Referred to Assignments
referral-committee - 2015-04-17 Senate Floor Amendment No. 3 Filed with Secretary by Sen. Chapin Rose
amendment-introduction - 2015-04-17 Senate Floor Amendment No. 3 Referred to Assignments
referral-committee - 2015-04-21 Second Reading
reading-2 - 2015-04-21 Placed on Calendar Order of 3rd Reading April 22, 2015
- 2015-04-21 Senate Floor Amendment No. 2 Assignments Refers to Energy and Public Utilities
- 2015-04-21 Senate Floor Amendment No. 3 Assignments Refers to Energy and Public Utilities
- 2015-04-23 Senate Floor Amendment No. 2 Postponed - Energy and Public Utilities
- 2015-04-23 Senate Floor Amendment No. 3 Postponed - Energy and Public Utilities
- 2015-04-24 Rule 2-10 Committee/3rd Reading Deadline Established As May 15, 2015
- 2015-04-29 Senate Floor Amendment No. 4 Filed with Secretary by Sen. Chapin Rose
amendment-introduction - 2015-04-29 Senate Floor Amendment No. 4 Referred to Assignments
referral-committee - 2015-05-05 Senate Floor Amendment No. 5 Filed with Secretary by Sen. Chapin Rose
amendment-introduction - 2015-05-05 Senate Floor Amendment No. 5 Referred to Assignments
referral-committee - 2015-05-06 Senate Floor Amendment No. 5 Assignments Refers to Energy and Public Utilities
- 2015-05-06 Senate Floor Amendment No. 4 Pursuant to Senate Rule 3-8(b-1), the following amendment will remain in the Committee on Assignments
- 2015-05-07 Senate Floor Amendment No. 5 Recommend Do Adopt Energy and Public Utilities; 013-000-000
- 2015-05-07 Recalled to Second Reading
reading-2 - 2015-05-07 Senate Floor Amendment No. 5 Adopted; Rose
amendment-passage - 2015-05-07 Placed on Calendar Order of 3rd Reading
- 2015-05-07 Third Reading - Passed; 055-000-000
reading-3, passage - 2015-05-07 Senate Floor Amendment No. 2 Tabled Pursuant to Rule 5-4(a)
amendment-failure - 2015-05-07 Senate Floor Amendment No. 3 Tabled Pursuant to Rule 5-4(a)
amendment-failure - 2015-05-07 Senate Floor Amendment No. 4 Tabled Pursuant to Rule 5-4(a)
amendment-failure - 2015-05-07 Arrived in House
introduction - 2015-05-07 Chief House Sponsor Rep. Brandon W. Phelps
- 2015-05-07 First Reading
reading-1 - 2015-05-07 Referred to Rules Committee
referral-committee - 2015-05-13 Final Action Deadline Extended-9(b) May 22, 2015
- 2015-05-13 Assigned to Public Utilities Committee
referral-committee - 2015-05-20 Do Pass / Short Debate Public Utilities Committee; 011-000-000
committee-passage - 2015-05-20 Placed on Calendar 2nd Reading - Short Debate
- 2015-05-21 Second Reading - Short Debate
reading-2 - 2015-05-21 Placed on Calendar Order of 3rd Reading - Short Debate
- 2015-05-22 Final Action Deadline Extended-9(b) May 31, 2015
- 2015-05-28 Third Reading - Short Debate - Passed 116-000-000
reading-3, passage - 2015-05-28 Added Alternate Chief Co-Sponsor Rep. Jack D. Franks
- 2015-05-28 Added Alternate Chief Co-Sponsor Rep. Carol Ammons
- 2015-05-28 Added Alternate Chief Co-Sponsor Rep. Carol Sente
- 2015-05-28 Added Alternate Chief Co-Sponsor Rep. Linda Chapa LaVia
- 2015-05-28 Added Alternate Chief Co-Sponsor Rep. Donald L. Moffitt
- 2015-05-28 Alternate Chief Co-Sponsor Removed Rep. Linda Chapa LaVia
- 2015-05-28 Added Alternate Co-Sponsor Rep. Linda Chapa LaVia
- 2015-05-28 Added Alternate Co-Sponsor Rep. Patrick J. Verschoore
- 2015-05-28 Passed Both Houses
- 2015-06-26 Sent to the Governor
executive-receipt - 2015-08-18 Governor Approved
executive-signature - 2015-08-18 Effective Date August 18, 2015
- 2015-08-18 Public Act . . . . . . . . . 99-0399
became-law