type, title, description, jurisdiction, legislature, session, identifier, citation, classification, subjects, status, primary_sponsors, version_count, action_count, vote_count, first_action, last_action, source, source_identifier, source_url, source_hash, vintage, source_snapshot, retrieved_at, confidence, tags
type title description jurisdiction legislature session identifier citation classification subjects status primary_sponsors version_count action_count vote_count first_action last_action source source_identifier source_url source_hash vintage source_snapshot retrieved_at confidence tags
Bill Electric utility reliability adequacy metrics. Provides that a public utility (defined in the bill as a utility listed in the utility regulatory commission's (IURC's) rule concerning integrated resource planning) that owns and operates an electric generating facility serving Indiana customers shall operate and maintain the facility using good utility practices and in a manner: (1) reasonably intended to support the provision of reliable and economic electric service to customers; and (2) reasonably consistent with the resource reliability requirements of the Midcontinent Independent System Operator (MISO) or any other appropriate regional transmission organization. Provides that, not later than 30 days after the deadline for submitting an annual planning reserve margin report to MISO, each public utility providing electric service to Indiana customers shall file with the IURC a report that provides the following information for each of the next three resource planning years: (1) The capacity, location, and fuel source for each electric generating facility that is owned and operated by the electric utility, and that will be used to provide electric service to Indiana customers. (2) The amount of generating resource capacity or energy, or both, that the public utility has procured under contract, and that will be used to provide electric service to Indiana customers. (3) The amount of demand response resources available to the public utility under contracts and tariffs. (4) The planning reserve margin requirements and other federal reliability requirements that the public utility is obligated to meet, including a comparison of each reported planning reserve margin requirement with the planning reserve margin requirement for the 2021-2022 planning year. (5) The reliability adequacy metrics (as defined in the bill) for the public utility, as forecasted for the three planning years covered by the report. Provides that in reviewing a public utility's report, the IURC may request technical assistance from MISO or any other appropriate regional transmission organization in making certain determinations concerning the adequacy of the public utility's available capacity resources to support the provision of reliable electric service. Provides that if, after reviewing a public utility's report, the IURC is not satisfied that the public utility can: (1) provide reliable electric service to the public utility's Indiana customers; or (2) meet its planning reserve margin requirement or other federal reliability requirements; during any of the planning years covered by the report, the IURC may conduct an investigation as to the reasons. Provides that if, after such an investigation, the IURC determines that the capacity resources available to the public utility will not be adequate to support the provision of reliable electric service to the public utility's Indiana customers, or to allow the public utility to meet its planning reserve margin requirements or other federal reliability requirements, the IURC shall issue an order directing the public utility to acquire or construct such capacity resources as are reasonable and necessary to enable the public utility to meet these requirements. Provides that not later than 90 days after the date of such an order by the IURC, the public utility shall file for approval with the IURC a plan to comply with the order. Provides that the IURC shall annually submit to the governor and to the interim study committee on energy, utilities, and telecommunications a report that includes the following: (1) The IURC's analysis regarding the ability of public utilities to: (A) provide reliable electric service to Indiana customers; and (B) meet their planning reserve margin requirements or other federal reliability requirements; for the next three resource planning years. (2) A summary of: (A) the projected demand for retail electricity in Indiana over the next calendar year; and (B) the amount and type of capacity resources committed to meeting this demand. Authorizes the IURC to adopt rules to implement these provisions. us/states/in Indiana General Assembly 2021 HB 1520 Indiana HB 1520 (2021)
bill
ELECTRICAL SERVICE
CONTRACTORS AND TECHNICIANS
UTILITIES
UTILITY REGULATORY COMMISSION
enacted
Edmond Soliday
Eric Koch
Mark Messmer
4 20 1 2021-01-14 2021-04-15 openstates ocd-bill/ff59fe2e-858a-439a-a638-5cbcbf4e965f http://iga.in.gov/legislative/2021/bills/house/1520 1285b1587c1ed77a29648a192601cafcb969c51a785eebdda386de97ddaefc1e 2026-07-01 https://data.openstates.org/daily/2026-07-01/public.pgdump 2026-07-06 reported
legislation
bill
us-in

Indiana HB 1520 (2021) — Electric utility reliability adequacy metrics.

Provides that a public utility (defined in the bill as a utility listed in the utility regulatory commission's (IURC's) rule concerning integrated resource planning) that owns and operates an electric generating facility serving Indiana customers shall operate and maintain the facility using good utility practices and in a manner: (1) reasonably intended to support the provision of reliable and economic electric service to customers; and (2) reasonably consistent with the resource reliability requirements of the Midcontinent Independent System Operator (MISO) or any other appropriate regional transmission organization. Provides that, not later than 30 days after the deadline for submitting an annual planning reserve margin report to MISO, each public utility providing electric service to Indiana customers shall file with the IURC a report that provides the following information for each of the next three resource planning years: (1) The capacity, location, and fuel source for each electric generating facility that is owned and operated by the electric utility, and that will be used to provide electric service to Indiana customers. (2) The amount of generating resource capacity or energy, or both, that the public utility has procured under contract, and that will be used to provide electric service to Indiana customers. (3) The amount of demand response resources available to the public utility under contracts and tariffs. (4) The planning reserve margin requirements and other federal reliability requirements that the public utility is obligated to meet, including a comparison of each reported planning reserve margin requirement with the planning reserve margin requirement for the 2021-2022 planning year. (5) The reliability adequacy metrics (as defined in the bill) for the public utility, as forecasted for the three planning years covered by the report. Provides that in reviewing a public utility's report, the IURC may request technical assistance from MISO or any other appropriate regional transmission organization in making certain determinations concerning the adequacy of the public utility's available capacity resources to support the provision of reliable electric service. Provides that if, after reviewing a public utility's report, the IURC is not satisfied that the public utility can: (1) provide reliable electric service to the public utility's Indiana customers; or (2) meet its planning reserve margin requirement or other federal reliability requirements; during any of the planning years covered by the report, the IURC may conduct an investigation as to the reasons. Provides that if, after such an investigation, the IURC determines that the capacity resources available to the public utility will not be adequate to support the provision of reliable electric service to the public utility's Indiana customers, or to allow the public utility to meet its planning reserve margin requirements or other federal reliability requirements, the IURC shall issue an order directing the public utility to acquire or construct such capacity resources as are reasonable and necessary to enable the public utility to meet these requirements. Provides that not later than 90 days after the date of such an order by the IURC, the public utility shall file for approval with the IURC a plan to comply with the order. Provides that the IURC shall annually submit to the governor and to the interim study committee on energy, utilities, and telecommunications a report that includes the following: (1) The IURC's analysis regarding the ability of public utilities to: (A) provide reliable electric service to Indiana customers; and (B) meet their planning reserve margin requirements or other federal reliability requirements; for the next three resource planning years. (2) A summary of: (A) the projected demand for retail electricity in Indiana over the next calendar year; and (B) the amount and type of capacity resources committed to meeting this demand. Authorizes the IURC to adopt rules to implement these provisions.

Version chain

The bill's text revisions, in order — the diff chain from filing to enrollment.

  1. Enrolled House Bill (H) (committee substitute) — source
  2. House Bill (H) (committee substitute) — source
  3. House Bill (S) (committee substitute) — source
  4. Introduced House Bill (H) (committee substitute) — source

Votes

  • HB 1520 - Koch - 3rd Reading — 500 (pass) · upper

Sponsors

  • Edmond Soliday — primary (person)
  • Eric Koch — primary (person)
  • Mark Messmer — primary (person)
  • Ethan Manning — coauthor (person)
  • Jean Breaux — cosponsor (person)
  • Lonnie Randolph — cosponsor (person)

Timeline

The legislative action history — every referral, reading, and vote.

  • 2021-01-14 Authored by Representative Soliday
  • 2021-01-14 First reading: referred to Committee on Utilities, Energy and Telecommunications reading-1, referral-committee
  • 2021-02-04 Committee report: amend do pass, adopted committee-passage
  • 2021-02-08 Representative Manning added as coauthor
  • 2021-02-08 Second reading: ordered engrossed reading-2
  • 2021-02-11 Senate sponsors: Senators Koch and Messmer
  • 2021-02-11 Third reading: passed; Roll Call 114: yeas 93, nays 0 passage, reading-3
  • 2021-02-12 Referred to the Senate
  • 2021-02-23 First reading: referred to Committee on Utilities reading-1, referral-committee
  • 2021-03-25 Committee report: do pass, adopted committee-passage
  • 2021-03-29 Second reading: ordered engrossed reading-2
  • 2021-03-30 Third reading: passed; Roll Call 298: yeas 50, nays 0 passage, reading-3
  • 2021-03-30 Senator Breaux added as cosponsor
  • 2021-03-30 Senator Randolph added as cosponsor
  • 2021-03-31 Returned to the House without amendments
  • 2021-04-07 Signed by the Speaker
  • 2021-04-08 Signed by the President Pro Tempore
  • 2021-04-14 Signed by the President of the Senate
  • 2021-04-15 Signed by the Governor executive-signature
  • 2021-04-15 Public Law 60