Files
republic-os/legal/us/code/title-33/chapter-36/section-2344.md
T
Fabio 76b8ec33a7 Legal corpus: the complete U.S. Code (59,740 sections, all 53 titles)
Ingested titles 12–51 and 54 from OLRC USLM XML @119-100 (the whole Code
now, uniform edition; Title 53 is reserved/empty). LegalText 11,221 ->
59,740; repo total 105,704 records. Deterministic (byte-identical rerun,
verified on Title 42's 8,356 sections); make check green. make
legal-us-code default now covers every title.

Co-Authored-By: Claude Opus 4.8 <noreply@anthropic.com>
2026-07-06 10:51:44 -04:00

5.0 KiB
Raw Blame History

type, title, description, jurisdiction, corpus, kind, title_number, title_name, chapter_number, chapter_name, section, citation, status, release_point, release_date, source, source_url, source_identifier, source_file, source_hash, raw_snapshot_hash, text_hash, retrieved_at, confidence, tags
type title description jurisdiction corpus kind title_number title_name chapter_number chapter_name section citation status release_point release_date source source_url source_identifier source_file source_hash raw_snapshot_hash text_hash retrieved_at confidence tags
LegalText 33 U.S.C. § 2344 Safety assurance review us united_states_code code_section 33 NAVIGATION AND NAVIGABLE WATERS 36 WATER RESOURCES DEVELOPMENT 2344 33 U.S.C. § 2344 current 119-100 2026-06-26 official https://uscode.house.gov/download/releasepoints/us/pl/119/100/xml_usc33@119-100.zip /us/usc/t33/s2344 data/legal/raw/us/code/title-33/usc33.xml 8e8967a33e3ac178f0479b5b5ba7b29f5fecea7aa09e770a9fbb8aed3dbcab2c de3d130b31eae77f8c0fc593f61b7287899297718d678d500eea123559828523 b6cd1a306d21c0af5816b4ea9c99882803dba0e6f33c393a2e5d0f5efa21d313 2026-07-04 official
legal
us-code

33 U.S.C. § 2344 - Safety assurance review

Text

(a) Projects subject to safety assurance review The Chief of Engineers shall ensure that the design and construction activities for hurricane and storm damage reduction and flood damage reduction projects are reviewed by independent experts under this section if the Chief of Engineers determines that a review by independent experts is necessary to assure public health, safety, and welfare.

(b) Factors In determining whether a review of design and construction of a project is necessary under this section, the Chief of Engineers shall consider whether—

(1) the failure of the project would pose a significant threat to human life;

(2) the project involves the use of innovative materials or techniques;

(3) the project design lacks redundancy; or

(4) the project has a unique construction sequencing or a reduced or overlapping design construction schedule.

(c) Safety assurance review (1) Initiation of review At the appropriate point in the development of detailed engineering and design specifications for each water resources project subject to review under this section, the Chief of Engineers shall initiate a safety assurance review by independent experts on the design and construction activities for the project.

(2) Selection of reviewers A safety assurance review under this section shall include participation by experts selected by the Chief of Engineers from among individuals who are distinguished experts in engineering, hydrology, or other appropriate disciplines. The Chief of Engineers shall apply the National Academy of Sciences policy for selecting reviewers to ensure that reviewers have no conflict of interest with the project being reviewed.

(3) Compensation An individual serving as an independent reviewer under this section shall be compensated at a rate of pay to be determined by the Secretary and shall be allowed travel expenses.

(d) Scope of safety assurance reviews A safety assurance review under this section shall include a review of the design and construction activities prior to the initiation of physical construction and periodically thereafter until construction activities are completed on a regular schedule sufficient to inform the Chief of Engineers on the adequacy, appropriateness, and acceptability of the design and construction activities for the purpose of assuring public health, safety, and welfare. The Chief of Engineers shall ensure that reviews under this section do not create any unnecessary delays in design and construction activities.

(e) Safety assurance review record The written recommendations of a reviewer or panel of reviewers under this section and the responses of the Chief of Engineers shall be available to the public, including through electronic means on the Internet.

(f) Applicability This section shall apply to any project in design or under construction on November 8, 2007, and to any project with respect to which design or construction is initiated during the period beginning on November 8, 2007, and ending 7 years after November 8, 2007.

(g) Nonapplicability of chapter 10 of title 5 Chapter 10 of title 5 shall not apply to a safety assurance review conducted under this section.

(Pub. L. 110114, title II, § 2035, Nov. 8, 2007, 121 Stat. 1091; Pub. L. 113121, title III, § 3028, June 10, 2014, 128 Stat. 1305; Pub. L. 117286, § 4(a)(204), Dec. 27, 2022, 136 Stat. 4328.)

Notes

Editorial Notes

Codification Section was enacted as part of the Water Resources Development Act of 2007, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.

Amendments2022—Subsec. (g). Pub. L. 117286 substituted “chapter 10 of title 5” for “FACA” in heading and “Chapter 10 of title 5” for “The Federal Advisory Committee Act (5 U.S.C. App.)” in text. 2014—Subsec. (g). Pub. L. 113121 added subsec. (g).

Statutory Notes and Related Subsidiaries

“Secretary” Defined Secretary means the Secretary of the Army, see section 2 of Pub. L. 110114, set out as a note under section 2201 of this title.